Question :

COIT12208 Assessment item 2 — Individual case studyIntroduction and Student Guide

This assessment item is to be completed individually.

The case study simulates a project management scenario where the student takes on the role of project manager.  The case information is not complete so where necessary students will have to argue the pros and cons of any assumptions they make. If necessary, students are expected to find relevant information in the academic literature to justify their answers and provide appropriate references.

The following information is provided to assist students to develop their assessment solution:

  • Product development case description
  • Specific assessment questions that must be answered
  • Information regarding the submission of the assessment 
  • Marking guide 

Important notes regarding assignment submission

  1. You must aim to submit your assignment at least 1 hour before the due date. This will avoid unnecessary late penalties if you have any technical issues while submitting your assignment.
  2. If you do have a problem uploading your assignment online and cannot get help from TASAC, make sure that you email your assignment files to your tutor before the due date. This will allow your tutor to view the work that was completed before the deadline. Note that you will also be required to submit the assignment online through Moodle.
  3. Any drafts in Moodle may be automatically submitted by Moodle at the due date. However, you must not rely on this for your submission. Note that this does mean that you should not leave something uploaded as a draft if you do not want it to be submitted automatically. If you upload after the due date (this includes students with extensions) you must ensure that you press ‘submit for marking’ or you may incur a further late penalty.

Preparation for the assignment

  1. You must complete the MP practicals 1 and 2 before you start this assignment.
  2. You must also complete practical 3 before you attempt to add resources to your assignment.

You are required to take your Microsoft Project practical’s and this assignment to your tutorial/practical classes from week 3 onwards. The course is scheduled to commence the practical’s in week 3 and you are expected to start work on this assignment in week 6 (or earlier).

The Mo Mo Factory Outlet Case Description 

The last four years had been a roller coaster ride for the companies three founders Raju, Vaneet and Dipesh. The readymade Nepalese’s dumpling (Mo Mo) business had exploded before their eyes.  Their choice of street front premises had proved very successful. As the business expanded they were able to grow with the acquisition of a warehouse at the rear of the property from which they were able to manufacture and dispatch there product to restaurants and supermarkets across Sydney and with the capacity to produce product for the whole of Australia and beyond.    

The next stage of growth comes with some substantial constraints which will direct the nature of future projects.  The easiest thing to do, is more of the same but that requires extending the geographic reach of its distribution which in turn, pushes up costs. The last few months have shown that the wholesales customer base would not tolerate the required price increase. Forays into the Brisbane and Melbourne markets have cost the company dearly and left the company strapped for cash. The only positive outcome from these trials, was the knowledge gained to structure air flight delivery to those capitals.

To revitalise the company’s fortunes and to pay for the up keep of the company yacht,  Rakshya, Aashish and Dipesh have put together a plan to grow the business and change the business model and revenue stream of the company.   

The Mo Mo Factory are to risk cannibalising there exiting business and to start selling directly to the general public. The project will involve setting up retail outlets in 10 shopping centre food court in each of the three eastern seaboard capitals. 30 shops in all. 

Project work has been divided into 7  sections from which you the Project manager will create the WBS for the project 
1.0Fund Raising 
2.0Securing retail spaces
3.0Retail Spaces Fit out
4.0Systems Development
5.0Hardware Acquisition
6.0Staff Acquisition and training
7.0Marketing and promotion

As old Alumni’s of CQU Rakshya, Aashish and Dipesh had come to the college and requested your help to turn their plan into a set of MS project worksheets. You will carry out this work individually with the assistance of your tutor.

You have responsibility for scheduling the work of a team of 16 professionals and will need to manage their labour, accommodation and air travel costs. Other transport and material costs will be incorporated into the Mo Mo Factory’s operational cost centre and will not be included in your MS Project plan. You also do not need to include your our own labour cost/resources and that of Rakshya, Aashish and Dipesh in the MS project files.

Rakshya, Aashish and Dipesh have left some notes that formed the basis of the plan and your structure for your WBS in your Ms Project in this table below. 

<

Show More

Answer :

The MoMo Factory is in the business of selling readymade Nepalese’s dumplings and selling them through supermarkets and various restaurants. In order to expand the business, the founding members have decided to set up 30 retail outlets in order to start selling directly to the general public. The plan is to set up 10 retail outlets in shopping centre food courts in each of the three Australian capital cities of Sydney, Brisbane and Melbourne.

The following pages provide the plan details, accompanied with MS-Project plan for the team of 16 professionals. The attachments include:

MMFO_PartAQ1.mpp: This file presents the scheduled tasks with original scenario as provided by the founding members. The duration of the project comes to 129 days with a total cost of $828,675.60. However, there is some resource over allocations in this version. Additionally, the cost for some resources has been assumed as follows:

MMFO_PartAQ1.mpp

WBSTask NameComments/task sequenceEffort and Resources 
1.0Fund Raising  Project start date 10th June 20193 weeks   Rakshya, Aashish and Dipesh. (Don’t show these resources in the project plan )
2.0Securing retail spacesStart after fund raising A region manager will be recruited at each site. 
2.1Determine locations Work can be done simultaneously in each region 2 weeks simultaneous work by each of the three RM’s 
2.2Negotiate rental contractAfter Determining Location 2.24 weeks of 3 RM’s
2.3Review and Sign ContractsAfter Review and Sign Contracts2 weeks 1 RM 
3.0Retail Spaces Fit out

3.1  CarpentryAfter the Review & Sign Contract. 5.1.4 carpentry work can commence. Three days each shopping centre
3.1.1Sydney
30days of 2 SF and 10% of RM
3.1.2MelbourneStart After Sydney30days of 2 SF and 10% of RM
3.1.3BrisbaneStart after Sydney30days of 2 SF and 10% of RM
3.2   Electrics
One days each shopping centre
3.2.1SydneyStart once Carpentry in Sydney is complete 2.1.110days of 2 SF and 10% of RM
3.2.2MelbourneStart once Carpentry in Melbourne is complete 2.1.210days of 2 SF and 10% of RM
3.2.3BrisbaneStart once Carpentry in Brisbane is complete 2.1.310days of 2 SF and 10% of RM
3.3  PlumbingWork can be done at each site at the same timeTwo  shopping centres each day
3.3.1SydneyStart once Electrics in Sydney is complete 2.2.15 days of 2 SF and 10% of RM
3.3.2MelbourneStart once Electrics in Melbourne is complete 2.2.25 days of 2 SF and 10% of RM
3.3.3BrisbaneStart once Electrics Brisbane is complete 2.2.35 days of 2 SF and 10% of RM




4.0Systems DevelopmentThe Mo Mo factory did not set out to replace information systems for this project , but it soon became clear that sound financial control and accurate demand pull, product delivery were essential.

7 software modules were Identified. All will be cloud hosted services but will require substantial configuration.    Discussion with software engineers indicated this section would take 70 days. Diagram below turned out to be an over simplification with more detailed dependences outlined in the inserted table below the diagram. 
Each module has multiple tasks Each task requires multiple resources (these are summary headings and we never assign resources to summary headings)

4.1Manufacturing Resource ProcessingThe BA later explained first module 4.1 was in fact 5 tasks shown in the next 5 rows. Details of the other modules:  4.2,4.3,4.4,4.5 were later forwarded in an e-mail in table form ( below ) as the  associated tasks were similar.
4.1.1   Inventory controlAfter IB Acceptance 1.1.2 wks of Business Analysts (BA) ,Software Engineer (SE) and Production Specialist (PS)
4.1.2   Modelling production lines  After inventory control 5.1.12 wks of Business Analysts (BA) ,Software Engineer (SE) and Production Specialist (PS)
4.1.3

   Capacity planning
After inventory control 5.1.11 wks Software Engineer (SE) and Production Specialist (PS)
4.1.4   Live production reportingAfter Modelling production Lines   5.1.2 and Capacity Planning 5.1.33 Days  Business Analysts (BA) Software Engineer (SE) and Production Specialist (PS)
4.1.5   IntegrationsAfter Activity learning 5.1.22 Day of Business Analysts (BA) , Software Engineer (SE) and Production Specialist (PS)

The other software modules all have similar tasks so have been arranged in this table below

Task Name \Module4.2 Logistics4.3 Human Resource Roistering4.4 Point of Sales System4.5 Purchase Order4.6 General ledgerComments

Duration
Requirements Analysis /codes Identification3 days with BA, RM,PS2 wks BA, RM, PS4 wks BA, RM, CH,EM2 wks BA, RM4 days BA, Start after Fund Raising1 1.0 and relevant testing of previous modules per network diagram above.
Process Configuration1 wk BA,SE,PS4 days BA, SE 3 wks BA, SE, RM1 wk BA, SE1 wk
BA
After requirements Analysis/Codes identification
System population1 wks SE,PS2 wks SE, RM2 wks CH, SE and PS3 wks SE

3 days BA, CH,PS, RM
Start after process configuration is tested
Test2 days SE, PS4 days SE, RM2 wks SE, RM3 days SE & PS, RM2days BA, RMStart after system population

In addition to these instructions the BA tells you the Logistics requirements 4.2.1 cannot be started until Inventory Control 4.1.1 has completed 




5HardwareTo fit out at each of the 30 locations
   Micro Wave
   Point of Sale equipment
   LCD Screens
   Warmer cabinets
   Bins
    .  
Don’t need to include these capital resources in the plan.
5.1Hardware OrderThe day after the IB Acceptance 1.0
5.1.1  Develop Tender DocumentAfter IB acceptance6 days work for BA, RM, PS, EM & CH
5.1.2  Open TenderAfter Develop Tender Document 5.1.12 weeks no resources
5.1.3  Award TenderAfter Open tender 5.1.21 day  BA & RM
5.1.4  Review & Sign ContractAfter Award tender 5.1.31 day  BA &RM
5.2.1Hardware ShippingAfter Sign review Contract 5.1.4. All equipment is delivered to Burwood NSW2 weeks, no resources
5.2.2Hardware received and checked 
4 Day PS,SF and EM
5.3 Food court outlet configuration Staff from Sydney will be used for these tasks. One SE / EM will travel in a hired van to each city meaning we can do only one region at a time in addition accommodation and van rental will need to be calculated for these tasks  

Van travel time in days between regions will need to be added to the task or new tasks created for capturing the correct labour and material
LocationSydneyMelbourneBrisbane
Sydney-2 days2 days
Melbourne2 days-5 days
Brisbane2 days5 days-

5.3.1Warmer Cabinet assemblyOn arrival of the Hardware 5.2. 1 days each site. Start or Finish in Sydney to avoid paying for weekend accommodation. 2 weeks of SF and EM and RM 10% per region plus travel time

Accommodation is $100 per unit/day
Van Hire are $50 per unit/day. (remember to add these in MS project as materials not work)
5.3.2    Servers/network½  days each site. Start or Finish in Sydney to avoid paying for weekend accommodation. Requires the network (5.3.1) to be in place. 6 days of SE. Should be done in conjunction with Network. Server will be delivered with Warmer Cabinets. SE can travel with the van or Fly down
5.3.3    POS AssemblyOn arrival of the Hardware 5.2. 2 days each site. Start or Finish in Sydney to avoid paying for weekend accommodation. Requires the Servers (4.1) to be in place.4 weeks of EM, SE and RM 10%. Per region plus travel time. Separate van trip delivering POS and LED Screens. Require accommodation while away from Sydney.  Van Hire and accommodation for EM 

5.3.4    LED Screen installationAfter 5.3.2 and 5.3.36 days of both CH & SE and  RM 10%.  Will require flights for the CH and accommodation

Sections 5.3.1 to 5.3.5 will need subtasks for the different location to provision the differing resource requirements The relevant team members will need to fly from the factory in Sydney to the other capitals to complete the work for each of these tasks. While others will travel by van. It will be necessary to make 2 van trips to each location one for Cabinets and server the other for POS and led’s as they won’t all fit in the first trip.These tasks will consume flight resources and Accommodation resources but only for the time away from Sydney. All of them will need van resources
Accommodation is $100 per unit
Flights are $200 per unit. Van Hire $50 per unit (remember to add these in MS project as materials not work)




6.0Staff Acquisition and training

6.1
Resource Name
Type
Std. Rate
Accommodation Cost Warmer Cabinet Assembly
Material
$5,000.00
Accommodation cost of SE
Material
$1,500.00
Flight and Accommodation for CH
Material
$2,000.00
POS Assembly Accommodation and Travel
Material
$3,000.00

MMFO_PartAQ2.mpp: This file presents the levelling of resources as done from previous file. As per requirement, the levelling options used are:

The change in project can be shown as follows:

MMFO_PartAQ1.mpp
MMFO_PartAQ2.mpp
Total Duration
Total Cost
Total Duration
Total Cost
129 days
$828,675.60
277 days
$828,675.60


The increased duration indicates the impact of levelling whereby the time taken has increased. 

The increase is very high as levelling was done with the requirement that no additional resources will be hired and they cannot be split. This is the reason that project cost remains same and only time increased.

Further, there is no change in ordering or sequence of tasks as the predecessor task as set in initial file have been kept same for this file also.

MEMO

To: The Founding Members, The MoMo Factory

From: Project Manager, XXX

Subject: Plan for Setting up Retail Outlets

Date: 24th May, 2019

The memo provides estimated plan for setting up of The MoMo Factory retail outlets in Sydney, Brisbane and Melbourne. Assuming that the project start date is 10th June, 2019, the estimated duration of the project is 277 days with the completion date being 22nd July, 2020. The total project cost is estimated at $828,675.60.

The initial project duration was estimated at 129 days but due to constraint of resource availability, the resources were levelled which increased the duration to 277 days. Most of the tasks are sequential in nature such that a task cannot begin simultaneously with previous tasks. However, the duration can be reduced by allocating more resources to tackle over-allocation aspect.

The direct cost has been estimated as:

Resource Name
Cost ($)
Regional Managers (RM)
1,97,785.60
Business Analysts (BA)
1,14,240.00
Production Specialist (PS)
61,560.00
Software Engineers (SE)
1,56,640.00
Catering and Hygiene Analyst (CH)
44,160.00
Shop Fitter (SF)
1,18,400.00
Electrical and Mechanical Engineer (EM)
78,400.00
Marketing Analyst (MA)
46,080.00
Total direct labour costs:
$8,17,265.60
Accommodation Cost Warmer Cabinet Assembly
5,000.00
Accommodation cost of SE
1,500.00
Flight and Accommodation for CH
2,000.00
POS Assembly Accommodation and Travel Cost
3,000.00
TOTAL COST
                $8,28,765.60 

Thank You,

XXX

Attachments: MMFO_PartAQ2

MMFO_PartAQ3.mpp: A copy of MMFO_PartAQ1 was created to see the over allocation of resources:

MMFO_PartAQ2

It can be seen that all the resources are over allocated but we have an option of increasing one resource only. Hence, the next step is to identify critical path through network diagram and see resource allocation for those resources. The identified resources on critical path are Regional Manager (RM) and Marketing Analyst (MA) but we have a constraint of increasing one resource from 100% to 200%. Hence, in this section, resource allocation has been increased for Marketing Analyst from 100% to 200%. This has been done by adding a resource called Additional Marketing Analyst at the same rate as MA and this has been allocated to WBS 7.1 to 7.4. The change is as follows:

MMFO_PartAQ1.mpp
MMFO_PartAQ3.mpp
Total Duration
Total Cost
Total Duration
Total Cost
129 days
$828,675.60
125.67 days
$831,985.60


It can be seen that duration has reduced by around 4 days at an additional cost of around $3,300 which is the cost of additional MA.

MMFO_PartAQ4.mpp: A copy of MMFO_PartAQ3 was created to see the over allocation of resources and level resources to tackle the issue:

 copy of MMFO_PartAQ3

 The change is as follows:

MMFO_PartAQ1.mpp
MMFO_PartAQ3.mpp
MMFO_PartAQ4.mpp
Total Duration
Total Cost
Total Duration
Total Cost
Total Duration
Total Cost
129 days
$828,675.60
125.67 days
$831,985.60
253.17 days
$831,985.60


It can be seen that after levelling, cost has remained same but impact is fully taken on duration as no additional resources have been hired. The total duration is now 253.17 days with a total cost of $831,985.60. The estimated project end date is 19th June, 2020.

All the resources were over allocated in initial file as seen above. Hence, it may be possible to reduce the duration by adding more resources as done for Marketing Analyst in initial stage.

Part A Q5: The quality issues that can hamper the project include:

  1. Quality Monitoring: Such a big project needs continuous quality monitoring at various points. For example, when carpentry or electrics or plumbing work is being done, a quality check is required before the task is signed off as complete.
  2. Project Monitoring: Again, a monitoring of the project and review at multiple levels is necessary to ensure that project is completed. With this kind of project, delays are natural and if not tracked and rectified as possible, it may increase project cost as well as duration.


The tasks that can be added are related to checking quality in first outlet before launching more outlets and another can be documenting the found results for perusal in further opening of new outlets:


WBS Number
Task Name
Predecessor’s
Duration 
Resource
8.0
Testing results from First Outlet
M5
15 days
Regional Managers
9.0
Quality Testing & Reports
8.0
15 days
Regional Managers


Part A Q6: As discussed above, project monitoring is a critical aspect for success of any project. Hence, this must be included at various steps so as to ensure that project remains on track in terms of cost as well as duration. This also helps to rectify deviations in a timely manner. For example, if a resource is in shortage, a call can be taken whether to hire additional resource or analyse effectiveness of current resource. 

Additionally, risk management should also be an integral part of any project so as to handle any risk arising in an effective manner.

Part B Q1: The Sprint has replaced the traditional module method under Point of Sales, leading to an increased overall duration of project from 277 days to 293 days and project ends on 13th August, 2020. This is due to predecessors for various tasks being changed to later tasks. 

For example, earlier, none of the Point of Sales tasks were critical to completion due to presence of slack period. Now, after Sprint method, Sprint 1 and Sprint 2 have become critical tasks as all slack has been utilized due to change of predecessor activity constraints.

Part B Q2: Earlier, none of the Point of Sales tasks were critical to completion due to presence of slack period. Now, after Sprint method, Sprint 1 and Sprint 2 have become critical tasks as all slack has been utilized due to change of predecessor activity constraints.


Change
Impact on project duration
(longer, shorter or no impact)

Explanation ( which resources and task clashes were the cause)
Removal of POS module  
Longer duration
Due to dependence on various tasks or changing of predecessors.
Addition 5.2.1 Sprint 1 
None
The task is a critical task now due to utilization of all the slack present earlier. There is over allocation of resources.
Addition 5.2.2 Sprint 2
None
The task is a critical task now due to utilization of all the slack present earlier.
Addition 5.2.3 Sprint 3
None
There is over allocation of resources.
Addition 5.2.4 Sprint 4
None
None

Part B Q3

Change
Impact on project Cost
(greater )

Explanation ( which additional resources were the cause)
Removal of POS Module
Greater at $263,400 
Addition of resources BA, RM, SE, EM, MA, if missing
Addition 5.2.1 Sprint 1 
Greater at $76,800 
Addition of resources BA, RM, SE, EM, MA, if missing
Addition 5.2.2 Sprint 2
Greater at $55,200 
Addition of resources BA, RM, SE, EM, MA, if missing
Addition 5.2.3 Sprint 3
Greater at $76,200 
Addition of resources BA, RM, SE, EM, MA, if missing
Addition 5.2.4 Sprint 4
Greater at $55,200 
Addition of resources BA, RM, SE, EM, MA, if missing

Part B Q4

A sprint methodology involves frequent meetings where a ScrumMaster or leader takes status update from team members and works towards removing obstacles in achieving goals so that the project stays on time. The methodology is collaborative in nature and hence, lines of communication need to be kept open. Further, it is necessary to hold frequent meetings so as to stay on set targets in the timeframe decided.

Hence, project manager needs to ensure clear communication about the timeframe and deadlines for smaller tasks involved in a stage so that team members use all their efforts to complete the task. Further, regular monitoring and meetings are necessary to identify roadblocks so that the project manager can clear the same and target can be met.